Weekly Report
Status update of Tavor-TD
1. RTL coding of Channel Estimation, approximately 30% done. (Bin)
2. Generate code coverage and function coverage report for Tx E-BIM. (Yun)
3. Study RM-HARQ design spec and write verification plan. (Yun)
4. Studying spec of channel estimation and matched filter. And begin to prepare test plan and test bench for channel estimation. (Chuntao)
5. Verifying Tx BIF with direct cases and random cases. Basically the functional verfication is almost done. (Gaohua, Weifeng)
6. Studying the LLD doc of JD Post processing. (Weifeng)
7. RTL coding of RM/HARQ. (Shengguo)
8. Work together with DSP team to setup FPGA environment. Debugging dsp’s spi driver, not closed yet. Coding spi’s wrap, and debugging using FPGA. (Shuo)
Plan for next week
1. Continue Tavor-TD RTL design, and deliver the 1st version source code for verification. (Bin)
2. Write testbench for HARQ and wait for random input definition for parameter C-model. (Yun)
3. Write basic reset and register test case for HARQ. (Yun)
4. Start testplan and testbench design for Channel Estimation. (Chuntao)
5. Close the Tx BIF verification with code and functional coverage reports. (Gaohua Weifeng)
6. Contine JD post processing LLD iterative discussion with Algr engineer and start micro-arch design. (Weifeng)
7. Deliver the 1st version source of HARQ for verification. (Shengguo)
8. Close SPI related issue and back to support codec related issues. (Shuo)